Infrastructure





City and county Infrastructure will be maintained and new projets will be started using SPLOST funds. This section includes the street maintanence and storm drainage projects.

Quick Stats
Infrastructure has 4 Focus Areas with a combined 16 projects. 7 of these projects are labeled in progress and 4 are complete.
pfs
FOCUS AREA TOTAL 2013 2014 2015 2016 2017
Macon Storm Drainage $7,000,000 $1,000,000 $1,207,922 $1,792,078 $2,000,000 $1,000,000
Street Maintenance $5,000,000 $1,000,000 $1,000,000 $2,000,000 $1,000,000
Bibb Storm Drainage $7,000,000
Bibb Street Maintenance $5,000,000